What is a 5x5 risk matrix?
A 5x5 risk matrix is a grid with five levels of likelihood on one axis and five levels of impact on the other. Multiplying the two gives a risk score from 1 to 25. The cells are color-coded, usually green for low risk through to red for very high risk.
It's the most widely used format in workplace safety, because five levels on each axis separate risks more finely than a 3x3 grid, while staying simple enough to use on the job.
5x5 risk matrix definitions
The template gives a starting set of definitions. Adjust them to suit your organization.
Likelihood
- Rare: not expected to happen in the life of the activity
- Unlikely: could happen, but only in unusual circumstances
- Possible: could happen at some point
- Likely: will probably happen in most circumstances
- Almost certain: expected to happen regularly
Impact
- Insignificant: no injury, or first aid only
- Minor: medical treatment, no lost time
- Moderate: lost-time injury or reversible illness
- Major: serious injury or permanent disability
- Catastrophic: one or more fatalities
Score bands
| Score | Rating | Action |
|---|---|---|
| 1–4 | Low | Manage with routine procedures |
| 5–9 | Medium | Plan controls; review regularly |
| 10–16 | High | Act promptly; senior approval to continue |
| 20–25 | Very high | Stop work until risk is reduced |
5x5 risk matrix example
Workers decant a corrosive cleaner from a 25-liter drum by tipping it into smaller bottles.
- Hazard: Splashes to the eyes and skin
- Likelihood: 4 (likely, as decanting happens daily)
- Impact: 4 (major, as an eye splash could cause permanent damage)
- Score: 16, high
- Controls: Use a drum pump, buy the product pre-diluted in smaller containers, provide goggles and a face shield, and install an eyewash station nearby
- Residual score: Likelihood 2 x impact 4 = 8, medium
The impact stays the same, because a splash would still be serious. The controls reduce the likelihood.
Risk matrix 3x3 vs. 5x5
A 3x3 matrix is quicker but groups many different risks into the same score. A 5x5 matrix separates them better, but it needs clear definitions so different assessors score the same hazard the same way.
ICAO and other 5x5 matrices
Some industries use their own versions. The ICAO safety risk matrix used in aviation, for example, combines five probability levels with five severity levels labeled A to E. The principle is the same.
Tips for consistent scoring
- Score with the current controls, then again with the new ones
- Pay extra attention to any risk with an impact of 5, whatever the total score
- Calibrate assessors by scoring a few known hazards together
- Write down who can accept a high risk, so decisions about continuing work aren't made informally
- Keep the matrix the same across sites, so scores can be compared fairly between them over time
Download the free 5x5 risk matrix template to standardize your risk scoring. For more on how the 5x5 matrix works, read our 5x5 risk matrix article.